But it is immediately, matter of CX89000 relationship production information
has entered the prospect information than STT like in ★ following contents.
Consider the delivery schedule look margin and in early August we believe the press production.
Contact manual "CX89000 CABINET BOTTOM / MIC GRILLE production GO" of SONY-like at the time of production
I would appreciate your favor because it becomes necessary. [Schedule of up to delivery] - September 05, STT-like delivery (500 to 1,000) and August 29 to September 02 days THAI SANEI finished goods and shipping and August 08 to August 26, 〃 surface treatment (blast - anodized aluminum laser other and inspection) and August 05 days SKK finished product and shipping - July 25 to August 04 SKK press production , July 21 to July 25, contact manual of the "press production GO" receive. Guidance of the test submission will be about maybe mid-August because it is the same timing as the original drawing transfer.